Science and Learning Center Project Remains on Schedule

Breadcrumb

June 4, 2015

President Herzberger, Project Manager John Best, VP Steve Delgado visit SLC sitePresident Sharon Herzberger and Whittier College officials donned hard hats and toured the Science and Learning Center construction site for the first time since the project began. Project Manager John Best gave President Herzberger and the group an update on the project’s progress and confirmed that it remains on schedule.

According to Best, the current phase will be completed by late June, followed by the installation of steel and concrete in the building’s interior commencing in July. The removal of the exterior pre-cast panels will follow in July. The building will begin to take its new shape in September, when installation of the exterior glass panels begins.

The design team used this renovation as an opportunity to retrofit the structure and improve its ability to withstand seismic motion. Replacing the exterior’s pre-cast panels with glass will make the Science and Learning Center lighter than its predecessor. Additionally, the building’s internal concrete walls will be wrapped with carbon fiber that will strengthen the structure.